Notices
January 26, 2007

Competing Request Submission Deadline for Non-firm Pre-Emption

 

 

Competing Request Submission Deadline for Non-firm Pre-Emption

 

Under SaskPower’s Pre-emption Business Practice and when scheduling deadlines fall on a weekend or holiday, all potential competing requests must be queued by 10:00 CST of the working day prior to the weekend or holiday for the purposes of non-firm pre-emption only.

 

For this purpose only and when scheduling deadlines fall on a Saturday or Sunday, potential competing requests must be queued by 10:00 CST on the preceding Friday.   The following holidays in 2007 also follow this criteria:

 

If the scheduling deadline falls on:

Competing Requests must be queued by:

February 19, 2007

February 16, 2007

April 6, 2007

April 5, 2007

April 9, 2007

April 5, 2007

May 21, 2007

May 18, 2007

July 2, 2007

June 29, 2007

August 6, 2007

August 3, 2007

September 3, 2007

August 31, 2007

October 8, 2007

October 5, 2007

November 12, 2007

November 9, 2007

December 25, 2007

December 24, 2007

December 26, 2007

December 24, 2007

 

If you would like further information on this business practice, please contact us at